Security of payment deadlines in every Australian state

Every state except the Northern Territory gives the person paying a progress claim a fixed number of business days to answer it. Miss that window and the full claimed amount can become payable, whatever the work was worth. The clock is short, it runs differently in each state, and it starts when the claim arrives, not when someone reads it.

How the deadlines work

The Acts follow the same pattern, with different numbers:

  • The claim. Anyone who carries out construction work or supplies related goods and services can serve a payment claim for a progress payment. Most states let you claim once a month, or as the contract allows.
  • The payment schedule. If the respondent doesn't intend to pay the whole claim, it must give a payment schedule within the state's time limit, stating the amount it will pay and every reason for withholding the rest.
  • Payment. The scheduled amount is due by the date the contract sets, but no later than the Act allows. A term that pushes payment past the cap has no effect.
  • Adjudication. If the claimant disagrees with the schedule, or isn't paid, it can apply for a fast, interim decision by an adjudicator.

Deadlines are counted in business days. Weekends and public holidays don't count, and nor does a stretch over Christmas, which varies by state. A contract can shorten these periods but not lengthen them.

Deadlines by state

For commercial work, counted in business days after the payment claim is served:

StatePayment schedulePayment dueNot business days
NSWWithin 10Principal to head contractor: 15. Head contractor to subcontractor: 2027 to 31 December
VICWithin 10No later than 20 business days22 December to 10 January
QLDWithin 15Principal to head contractor: 15. Head contractor to subcontractor: 2522 December to 10 January
WAWithin 15Principal to head contractor: 20. Head contractor to subcontractor: 2522 December to 10 January
SAWithin 15As the contract says; 15 business days if it says nothing27 to 31 December
TASWithin 10As the contract says; 10 business days if it says nothing27 to 31 December
ACTWithin 10No later than 15 business days27 to 31 December

A few state differences catch people out:

  • Victoria changed substantially on 15 April 2026. Payment is now capped at 20 business days (10 if the contract is silent), reference dates are gone, claims are monthly, and 22 December to 10 January no longer counts.
  • Queensland caps payment through the QBCC Act: 15 business days on a commercial head contract and 25 on a subcontract. Head contractors must also give a supporting statement about paying their subcontractors with each claim.
  • New South Wales has the shortest chain: 15 business days from the principal to the head contractor, and 20 from the head contractor to a subcontractor. Head contractors serve a supporting statement here too.
  • Western Australia's 2021 Act sets 20 business days down from the principal and 25 to a subcontractor, with the long Christmas shutdown.

Most states also require the claim to say it is made under the Act. The wording differs by state; leaving it out can make the claim invalid for adjudication.

A worked example

A subcontractor in Sydney emails a claim at 7:10pm on Friday 27 November 2026. The head contractor's payment schedule is due by Friday 11 December 2026, and the scheduled amount must be paid by Monday 4 January 2027.

Two things make this harder than it looks. The claim was served on the Friday, even though it arrived after hours and nobody opened it until Monday. And the payment date crosses the NSW shutdown, so 27 to 31 December and the public holidays around it are skipped. Count from Monday, or forget the shutdown, and you get the wrong day.

What a missed deadline costs

A respondent that gives no payment schedule in time, and doesn't pay, becomes liable for the whole claimed amount. The claimant can sue for it as a debt, and in NSW and several other states the respondent can't raise its defences to the claim in that case. It can also lose the right to put reasons to an adjudicator.

The courts apply the deadlines strictly. In 2025, the NSW Court of Appeal and the WA Supreme Court both held that a contract clause treating an after-hours or weekend email as received on the next business day did not move the start of the statutory clock. In the WA case, the claim was for about $22.6 million. Our guide to security of payment cases covers both, and the decisions that shaped how the Acts work.

Keeping track on a live job

A head contractor with twenty subcontractors gets twenty claims a month, each with its own clock, on top of its own claim to the principal. The failures are rarely about the law. They are about a claim sitting in someone's inbox over a long weekend, or a deadline worked out by hand without the shutdown.

What helps:

  • Record when each claim arrived, to the minute, in the time zone of the job.
  • Work out the schedule and payment dates as soon as the claim lands, and put them where the whole team can see them.
  • Draft the schedule from the work you can see on site, so reasons for withholding are specific and ready in time.
  • Know which subcontractors are owed money before you serve your own claim, if your state wants a supporting statement.

How Infrasis handles it

  1. Set the contract's state and terms

    Choose the state for each subcontract and the head contract. Infrasis won't accept payment terms longer than that state allows, and you can add local holidays the contract names.

  2. Serve or record the claim

    Subcontractors serve claims in Infrasis, or you record one that came by email with the time it arrived. The claim carries your state's wording.

  3. See both deadlines straight away

    The schedule and payment dates are counted in business days for that state, skipping weekends, public holidays and the Christmas shutdown. Both parties are notified.

  4. Schedule on time, from site progress

    The draft schedule starts from progress reported on site, inspections and open defects. A schedule given after the deadline is marked late, and the claimed amount stays payable.

Questions

Does the Northern Territory work the same way?

No. The NT Act uses a different process, built around notices of dispute and a response period set by the contract. Infrasis doesn't support NT contracts yet.

Do these deadlines apply to residential work?

The rules on this page are for commercial work. Several states treat contracts with a home owner differently, and some exclude them entirely. Check the Act for your state.

Is a claim served when it's sent or when it's opened?

Generally when it arrives where the respondent can retrieve it, which for email is usually when it reaches the nominated inbox. Recent decisions in NSW and WA say a contract clause deeming later receipt doesn't extend the statutory time.

Can the contract give us longer to pay?

Not beyond the state's cap. A contract can set a shorter time for the payment schedule or payment, but terms that exceed the Act's maximum are void, and the Act's period applies instead.

This page is general information, checked against the Acts and regulators' guidance in November 2026. It isn't legal advice: rules differ for residential work, final claims and particular contracts. For how claims are put together, see progress claims and payment schedules.