Inspection and Test Plans (ITPs) and quality records for builders

An Inspection and Test Plan says what gets checked on a piece of work, how, by whom, and what has to happen before the next step can start. On most jobs the plan is fine. What goes missing is the record: the hold point nobody signed, the certificate in someone's inbox, the NCR that was fixed but never closed.

What an ITP is

An ITP is written for a type of work, such as a slab pour, wet-area waterproofing or fire-stopping, and lists its checkpoints in the order they happen. Specifications on commercial jobs usually require one from each trade, and the head contractor or the principal's representative reviews it before the work starts.

Each checkpoint normally sets out:

  • What is checked, and the specification clause, drawing or Australian Standard it comes from.
  • How: looked at, measured, tested, or a document reviewed (a test certificate, a delivery docket).
  • What passes: the acceptance criteria, with a tolerance where something is measured.
  • Who checks it: the trade, the head contractor, or a third party such as a certifier, engineer or laboratory.
  • The kind of point, and the record that has to be kept: a photo, a measurement or a certificate.

Hold, witness and record points

  • Hold point. Work stops at this point until the named person inspects and releases it. Reinforcement before a pour and waterproofing before tiling are the classic examples, because the work is about to be covered up.
  • Witness point. The named person is given notice and may attend. If they don't come after proper notice, work can go on, and the record says so.
  • Record point. The check is done and recorded. Nobody waits.

A hold point applies to the work it covers. A hold on the bathroom waterproofing in an apartment shouldn't stop the electrician roughing in the bedrooms, so it helps when the system knows exactly which work a hold belongs to.

Third-party inspections

Some inspections belong to people outside the contract chain: the building certifier, the structural or fire engineer, a testing laboratory, the local authority, or the principal's representative. They are often hold points, and they are often added to work that the trade's own ITP doesn't mention, because a consent condition or an engineer's letter calls for them. The record needs to show who inspected, when, and their report or certificate.

Nonconformance reports

When work doesn't meet the requirement, an NCR records what was found and controls what happens next, so the work isn't covered up or built on by accident. A complete NCR has four parts:

  • The decision about the work: rework, repair, reject and replace, or use as is. Use as is normally needs the principal's or designer's written acceptance.
  • The cause, found by asking why it happened rather than who did it.
  • Corrective action, so it doesn't happen again on the next level.
  • Verification that the fix and the action worked, before the NCR is closed.

ITPs and ISO 9001

ISO 9001 is the quality management standard most head contractors are certified to. Its 2026 edition was published on 16 September 2026. Certificates to the 2015 edition stay valid during a three-year transition that ends on 30 September 2029, and the process approach and risk-based thinking carry over.

On a construction project, the auditor's questions about delivering the work come down to records:

  • Which version of the inspection plan was in force, and who approved it?
  • Was work released at each hold point, by the right person, before it went on?
  • Are the test results and certificates there for the work they cover?
  • Was nonconforming work controlled, and was the corrective action checked?

Certification is by an accredited certification body, and covers the whole management system, including the quality policy and objectives, internal audits and management review, as well as project records.

How Infrasis handles it

  1. ITPs under revision control

    Start from a standard plan for common work or write your own. Every change makes a new revision for someone to approve, and every record shows the revision it was checked against.

  2. A checklist on every lot

    Choose the ITP for a trade, and each location's work gets its checklist. Crews ask for releases, give witness notice and record checks from their phone, with photos and measurements against the tolerance.

  3. Holds that block the right thing

    An unreleased hold stops that lot being signed off, never the next trade in the location. Overrides need a written reason. Certifier, engineer and principal inspections can be added to any work.

  4. NCRs to verified close-out

    Decision, cause, corrective action and verification are each recorded with who and when. Open holds and NCRs are flagged on the payment schedule for you to decide.

  5. The quality pack

    Print the record for one lot, one trade or the whole project: the ITP register, the NCR register and every checkpoint with what was recorded. Infrasis puts in place the day-to-day controls an auditor checks, and keeps the records that prove they happened.

Questions

Is Infrasis an ISO 9001 certification?

No. Certification is by an accredited certification body, and covers your whole management system. Infrasis runs the project controls an auditor checks (inspection plans, hold points, third-party inspections and NCRs) and keeps the records, under both the 2015 and 2026 editions.

Can we use our own ITPs?

Yes. Write your company's ITPs in Infrasis checkpoint by checkpoint, or start from a standard plan and adjust it. Each project keeps its own approved revisions.

Do subcontractors need to use it?

Trades see the checklists on their own work and can ask for releases and record their own checks from the phone. A trade can't release its own hold point.

How do certifiers and engineers sign off?

Add them as an inspection company, and their inspection to the work. The head contractor records their sign-off on their behalf, with the company named and their report or certificate attached.

Is it compulsory on every job?

No. Quality checklists are switched on per project, and only the work you attach an ITP or inspection to is affected.

Sources